Dear Colleagues,

Following are the highlights of the Tuesday meeting:

Result:

Total No. of Magnet Test Cycle – 12

Actual No. of Tested Magnets – 12

Repeat Magnet- MBBL3138 and MBAL2182.

Tested SSS – SSS124

Tested Special SSS - SSS607 (Not mentioned in last week).

4000 special cycle on MBAL1084.

Magnetic Measurement on MBAR3348.

Problem encountered by SM18op Team:

Broken PLCSE Connector of HV rack.

TBD2 -quench during SPA because of the high Threshold value of potaim card.

TBE1-MXI error. Problem solved by resetting the server.

TBA2- Quench during special cycle.

TBB2- For IAP@warm LF heater discharge was not ok because Hardware Recognition was OFF for Test Bench B.

Due to high flow rate of He on TBA where was moisture condensation on Current Lead.

Due to the unavailability of correct Template for resistance measurement, there was an error with the resistance measurement on TBD1. It was solved by correcting the template.

HV rack XMT.MY95 is not working properly at High Voltage. Richard will look into problem.

Miscellaneous points of Meeting

TBB may be converted for Dipole test only.

SSW will be either on D1 or D2.

This is my last minutes of Tuesday meeting.

Wish you all nice weeks ahead.

Best regards

Prakash Kashyap