Dear All,

The following are the details of the meeting held on 1st March 2005

1. MTR page on the paper logbook for the quenches is modified. The operation team has to write down the " Maximum value of TauJumpV" in the MTR and also to match with the curves given in the quench analysis document for both quench heaters & voltage taps.

2. Siemko said they will implement a new version of AQA next week.

3. Open NC in the WP04 of the MTF, if the magnet name tag/label is not correct and notify. Please note down it at the new log on the 1st page of the MTR.

4. There will be one resistance file for the quadrupole called the CQR file. All the resistance measurement tests are Go/ NO GO tests. Generate the NC at the appropriate steps in the MTF (CQW1, CQBP etc.) if the resistance value does not confirm to the specified values for the particular test.

5. New card with filter to reduce the occurence of SPA of the PC is put on the D-cluster today.

Regards

Jitendra K Mishra